Highet Avenue road works

Brighton School Community-please note the following update I received regarding the Highet Avenue road works. PS Although this was forwarded yesterday, I was absent from school hence today’s post.

Ian

Council’s contractor is progressing well with the Highet Ave works as you would have noticed. There are some traffic restrictions coming up that you will need to be mindful of and please advise your school community. Most inconvenience will occur on weekend of 20/21 February, however this week there are some restrictions. It is recommended that parents utilise the entry to the carpark off Stopford Ave or off Brighton Rd for the impacted days. Would you please send the following information to the school community.

Work location Closed From Open
Cross over re-construction (Football car park entrance closed) Tuesday 9 Feb till Thursday 11 Feb Thursday afternoon 11 Feb 2021
Whole of Highet Ave closed for  reseal Saturday 20 Feb 21 Sunday afternoon 21 Feb 21
Whole of Highet Ave closed for line Marking Saturday 27 Feb 21 Saturday afternoon 27 Feb 21

 

 

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.